Trelyn overhead line, S37 Consent, Electricity Act 1989
Screening decision to replace a pole mounted transformer and a pole as part of an 11kV line.
Applies to Wales
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
29 August 2024
Location
Trelyn
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.