Trolver Croft Feock, Cornwall overhead line, S37 Consent, Electricity Act 1989
Screening decision to upgrade approximately 330 metres of an existing 11 kV overhead line to 3 wires, replace two poles and install a second pole to support pole mounted transformer upgrade.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
14 March 2025
Location
Trolver Croft Feock
Truro
Cornwall
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.