Screening decision to upgrade approximately 330 metres of an existing 11 kV overhead line to 3 wires, replace two poles and install a second pole to support pole mounted transformer upgrade.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

14 March 2025

Location

Trolver Croft Feock
Truro
Cornwall

Section 37 consent to install or keep installed an electric line.