Decision

Woodmancote, Cirencester, overhead line S37 Consent, Electricity Act 1989

Screening decision to upgrade 335 metres of existing 240/415v from single phase to 3 phase. Upgrade an existing pole mounted transformer.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

19 April 2024

Location

Woodmancote
Cirencester

Section 37 consent to install or keep installed an electric line.

Published 19 April 2024