Official Statistics

Planning Inspectorate statistical release 20 June 2024

Published 20 June 2024

Applies to England

1. Introduction

This statistical release provides summary information on appeals, which represent the highest volume (in terms of number of cases) of the Planning Inspectorate’s work.

These statistics are produced each month and the focus is on timeliness of decision-making, an area of particular interest for stakeholders. Information on the decisions that have been made is also included; and on the number of Inspectors available to make those decisions.

These statistics have been published to ensure everyone has equal access to the information and to support the Planning Inspectorate’s commitment to release information where possible.

This statistical bulletin provides: - Appeals decisions and events held from June 2023 to May 2024 - The time taken to reach decisions - Provisional estimates of the number of open cases - Number of Inspectors

The Planning Inspectorate

The Planning Inspectorate makes decisions and provides recommendations and advice on a range of land use and planning-related issues across England.

The Planning Inspectorate deals with planning appeals, national infrastructure planning applications, examinations of local plans and other planning-related and specialist casework in England. The Planning Inspectorate is an executive agency, sponsored by the Department for Levelling Up, Housing and Communities.

1.1 Summary

Time to decide cases

The median decision time for cases decided in May was 26 weeks.

Median timeliness by procedure type is shown in the summary table below.

Procedure type Last 12 months May 2024
Written Representations 30 weeks 26 weeks
Hearings 32 weeks 24 weeks
Inquiries 44 weeks 40 weeks
All Cases 30 weeks 26 weeks

The median time for planning cases was 25 weeks in May 2024. The 12-month median was 28 weeks.

Enforcement decisions made in May 2024 had a median decision time of 52 weeks, with the 12-month median being 53 weeks.

The median time for planning appeals decided by inquiry under the Rosewell Process in May was 30 weeks and over the 12 months to May 2024 was 30 weeks.

Decisions

The Planning Inspectorate made 18,412 appeal decisions in the last 12 months, an average of 1,534 per month. The number of decisions in May 2024 was 1,571.

There were 1,442 written representations decisions in May 2024 and 17,165 in the last 12 months.

There were 753 decisions made on hearings during the last 12 months, and during May 2024, 78 decisions were issued.

There were 494 decisions made on inquiries during the last 12 months, with 51 in May 2024.

Planning Inspectors

There were 443 Planning Inspectors employed by the Inspectorate at the end of May 2024.

2. Decisions, Events & Open Cases

The number of decisions issued in May 2024 was 1,571, with a monthly average of 1,534 over the past 12 months.

The number of events recorded for May 2024 was 1,398, the average over the past 12 months was 1,527.

The median valid to decision time was 26 weeks in May 2024, as seen in Figure 1 and Table 1 below. The median valid to decision time for May is 1.6 weeks shorter than for April.

There are no clear trends for the number of events and decisions per month. However, the Christmas and Easter breaks do typically impact on the number of events arranged for December and April.

Figure 1: Number of events held , decisions issued and median time between valid date & decision date; June 2023 to May 2024.

Source: Horizon

Table 1: Number of events held, decisions issued and median time between valid date & decision date; June 2023 to May 2024.

Note: This table includes revisions to previously published data. Please see Annex C for further information

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Events Held 1580 1431 1608 1496 1806 1619 1117 1898 1554 1240 1578 1398 18325
Decisions 1485 1516 1481 1619 1651 1607 1420 1508 1652 1452 1450 1571 18412
Median 31.6 33.3 31 31.4 30.4 31.9 29.4 30.1 28.4 27.8 27.6 26 29.9

Source: Horizon

Figure 2 below shows the number of cases received, closed and open for each of the last 12 months. The number of cases closed has exceeded the number of cases received for each of the past 12 months, with the exception of March 2024.

Note – The number of cases closed is higher than the number of decisions, as it includes cases where an appeal is withdrawn, notice is withdrawn, or the appeal is turned away.

Figure 2: Number of cases received, closed and open; June 2023 to May 2024.

Source: Horizon

Note: there is a known anomaly that means that the number of open cases does not exactly follow the volumes of cases closed or received (for example the number of open cases can increase between months even though the number closed exceeded the number received). The main reasons for this have been identified and are detailed in the Background Quality Report.

Table 2: Number of cases received, closed and open; June 2023 to May 2024.

Note 1: This table includes revisions to previously published data. Please see Annex C for further information

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Received 1614 1727 1607 1619 1680 1716 1459 1507 1617 1692 1563 1650 19451
Closed 1768 1738 1681 1825 1858 1818 1619 1754 1846 1671 1738 1778 21094
Open 14468 14450 14421 14203 14054 13809 13677 13546 13198 13254 13234 13137  

Source: Horizon

3. Number of Decisions

The Planning Inspectorate has made 18,412 appeal decisions in the last 12 months. There were 1,571 cases decided in May 2024.

Table 3 below shows the monthly breakdown with the highest number of decisions in February and lowest in December.

Table 3: Appeal Decisions; June 2023 to May 2024.

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Decisions 1485 1516 1481 1619 1651 1607 1420 1508 1652 1452 1450 1571 18412

Source: Horizon

Figure 3 – Appeal Decisions; June 2023 to May 2024.

Source: Horizon

Decisions by procedure and case type

Planning Inspectors work on a broader range of work than the appeals featured in this release. For example, they also work on examining Nationally Significant Infrastructure Project applications, Local Plans , Compulsory Purchase Order applications and many other specialist licencing/ application types.

Table 4 below gives the numbers of appeal decisions made broken down by whether the case was dealt with by written representations, hearings, or inquiries.

The large majority of decisions over the past 12 months (17,165) were made on written representations. This is 93% of all appeal decisions made. Table 4 shows that written representation decisions have varied from around 1,310 to around 1,560 per month over the past 12 months. There were 1,442 decisions in May 2024.

There were 753 decisions made on hearings during the last 12 months, the monthly average being 63. During May 2024, 78 decisions were issued. In May 2024, 51 decisions were made for inquiries. Decisions for inquiries per month over the last 12 months have ranged between 28 and 52.

Table 4: Appeal Decisions by Procedure and Casework Category; June 2023 to May 2024.

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Written Representations 1397 1417 1390 1515 1557 1492 1313 1406 1559 1330 1347 1442 17165
Hearings 59 65 63 58 54 66 64 67 49 79 51 78 753
Inquiries 29 34 28 46 40 49 43 35 44 43 52 51 494
Total 1485 1516 1481 1619 1651 1607 1420 1508 1652 1452 1450 1571 18412
Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Planning 1256 1256 1256 1338 1402 1337 1211 1246 1407 1131 1206 1325 15371
Enforcement 166 208 192 224 187 228 151 206 208 177 180 187 2314
Specialist 63 52 33 57 62 42 58 56 37 144 64 59 727
Total 1485 1516 1481 1619 1651 1607 1420 1508 1652 1452 1450 1571 18412

Source: Horizon

What are Planning cases? The Planning category includes s78 planning appeals, householder appeals, commercial appeals, listed building consent appeals, advertisement appeals, s106 planning obligation appeals and Called In Planning Applications.

What are Enforcement cases? Enforcement covers enforcement appeals (i.e., appeals against the issue of an enforcement notice served by a local planning authority for alleged breaches of planning control), enforcement listed building notice appeals and lawful development certificate appeals.

What are Specialist cases? Specialist casework includes Common Land, Rights of Way orders (including Schedule 14 cases), Purchase orders, Tree Preservation Orders, High Hedges appeals, Hedgerow appeals, Wayleave, Compulsory Purchase Orders, Secretary of State, Transport, Environmental Permitting Appeals and Coastal Access. Additional casework types have been added to this category over time.

The large majority of cases decided over the past 12 months were planning (15,371). This is about 83% of all appeal decisions made. There were 2,314 enforcement decisions and 727 specialist decisions. These totals are also shown in Table 4 above and Figure 4 below.

Trends for planning decisions show similar patterns to written representations. The average number of enforcement decisions over the past 12 months was 193. Specialist casework figures continue to vary each month, from a high of 144 in March 2024 to a low of 33 in August 2023.

Figure 4 – Appeal Decisions by Procedure and Casework Category; June 2023 to May 2024.

Source: Horizon

4. Decision timeliness

It is important for people to know how long an appeal is going to take, so that they can make informed plans and decisions. This section covers the timeliness of decisions (i.e., how long it takes to make a decision) across appeal casework. In addition to an overall measure, timeliness is analysed by procedure type and casework category, as timeliness varies a great deal depending on these characteristics.

Table 5 below shows that the median time to make a decision, across all cases in the last 12 months, was 30 weeks; and 26 weeks for May 2024. Figure 5 shows the median has ranged from 26 to 33 weeks for each of the last 12 months.

How is timeliness measured?

The time to make a decision is measured from the time the Inspectorate have enough information for the case to proceed (it is deemed ‘valid’) to the time a decision letter is issued. This means that any delay in ‘validating’ the appeal is included in the time to make a decision.

The decisions made in a given month will include those that started many months before, and thus do not give an accurate indication of how long appeals submitted, or deemed ‘valid’ in that month, will take.

Table 5 also shows the mean decision time for the last 12 months is 35 weeks. Each month the median is less than the mean, due to the impact of very long cases. Also included in the table is the standard deviation of decision timeliness, which is a measure of variation.

What are mean, median, and standard deviation?
Measure Definition
Mean The total time taken divided by the number of cases. Also referred to as the ‘average’. A measure of how long each case would take, if the total time taken was spread evenly across all cases.
Median This is the time taken by the ‘middle’ case if all cases were sorted from quickest to longest
Standard deviation This is a measure of variability or spread. It is calculated by examining how much each value differs from the mean. A higher standard deviation means the individual decision times vary more widely around the mean. A lower standard deviation would demonstrate greater consistency in the Planning Inspectorate’s decision timeliness.

Table 5: Median, mean and Standard Deviation of Time to Decision; June 2023 to May 2024

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Valid to Decision (median weeks) 31.6 33.3 31.0 31.4 30.4 31.9 29.4 30.1 28.4 27.8 27.6 26.0 29.9
Valid to Decision (mean weeks) 35.7 38.0 35.8 36.6 34.4 36.6 33.8 34.6 32.1 33.7 32.2 30.6 34.5
Standard Deviation (weeks) 20.4 21.9 20.8 21.5 18.8 20.7 19.8 20.3 18.7 21.6 20.0 19.3 20.4

Source: Horizon

Figure 5: Median and mean Time to Decision; June 2023 to May 2024.

Note: Specialist casework timeliness measures exclude Tree Preservation Order cases

Source: Horizon

Procedure Type

Table 6 below shows decision timeliness broken down by the procedure type. Hearings and inquires have typically been more variable than written representations . Because 19 of every 20 cases are by written representation, the timeliness measures for written representations are similar to the measure across all cases.

Where a small number of cases has been decided, the average timeliness (whether mean or median) is less meaningful as a measure than where there are many cases. Those noted in the table caption below should be treated with caution as there are fewer than 20 cases decided.

Median times are less affected by a small number of large values than mean times, so are the focus of this commentary. The median time for written representations over the 12 months to May 2024 is 30 weeks. The median time for hearings over the 12 months to May 2024 is 32 weeks. The median time to decide for inquiries over the 12 months to May 2024 was 44 weeks.

Table 6: Mean and Median Time to Decision, with Standard Deviation, by Procedure; June 2023 to May 2024.

Note 1: Where the number of decisions issued is fewer than 20, the measures mean, median and standard deviation are less meaningful.

Note 2: This table includes revisions to previously published data. Please see Annex C for further information

Key: WR= Written Representations; HRG= Hearings; INQ= Inquiries; All= All Cases

Measure Procedure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Valid to Decision (median weeks) WR 31.4 33.3 31.0 31.3 30.4 31.7 29.3 30.0 28.1 27.4 27.1 26.0 29.7
  HRG 33.6 32.9 29.6 32.0 28.1 32.1 33.6 38.9 38.3 27.4 40.4 24.3 31.8
  INQ 33.7 43.6 29.5 61.9 39.4 41.0 53.0 40.4 37.1 50.1 47.1 40.3 43.7
  All 31.6 33.3 31.0 31.4 30.4 31.9 29.4 30.1 28.4 27.8 27.6 26.0 29.9
Valid to Decision (mean weeks) WR 34.9 36.9 34.8 35.3 34.0 35.7 32.3 33.3 31.1 32.1 30.3 29.5 33.4
  HRG 44.4 52.1 49.0 47.2 43.0 43.1 45.4 50.9 44.9 44.9 52.8 34.4 45.7
  INQ 56.2 56.4 56.1 63.6 39.3 56.4 59.6 55.6 54.8 61.9 60.5 55.5 56.5
  All 35.7 38.0 35.8 36.6 34.4 36.6 33.8 34.6 32.1 33.7 32.2 30.6 34.5
Standard Deviation (weeks) WR 19.0 20.0 18.0 19.5 18.1 19.1 17.2 17.7 16.6 18.9 17.0 17.5 18.4
  HRG 29.4 37.2 40.1 36.6 34.2 27.1 30.4 39.7 26.1 34.0 39.3 22.7 33.8
  INQ 40.1 35.6 47.6 32.9 15.5 37.7 40.7 34.5 41.9 38.0 27.1 36.2 36.4
  All 20.4 21.9 20.8 21.5 18.8 20.7 19.8 20.3 18.7 21.6 20.0 19.3 20.4
Decisions WR 1397 1417 1390 1515 1557 1492 1313 1406 1559 1330 1347 1442 17165
  HRG 59 65 63 58 54 66 64 67 49 79 51 78 753
  INQ 29 34 28 46 40 49 43 35 44 43 52 51 494
  All 1485 1516 1481 1619 1651 1607 1420 1508 1652 1452 1450 1571 18412

Source: Horizon

Note: Tree Preservation Order cases are not included in timeliness measures

The standard deviation information indicates that for all three procedures, there is considerable variation, meaning times are widely spread about the mean. For written representations, the amount of variation has been quite stable over recent months, whereas inquiries have experienced considerable month to month changes in the spread of decision times.

Casework Category

The nature of the cases the Planning Inspectorate deal with varies widely and several factors play a part in determining how long it takes to make a decision. One such factor is the type of casework. Table 7 below shows the time taken to decide, in planning cases, in enforcement cases, and in specialist cases, as does Figure 6.

The median time to decision for planning cases (there are many more of these decisions than in the other categories) is lower than for enforcement cases; and less variable than the times for specialist cases. Table 7 and Figure 6 show the median time for planning cases has been 26 weeks and above for each of the last twelve months.

Table 7: Decisions, Mean, Median and Standard Deviation of Time to Decision – Planning, Enforcement, Specialist Cases; June 2023 to May 2024.

Note 1: This table includes revisions to previously published data. Please see Annex C for further information

Casework Category Measure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Planning Cases Valid to Decision (median weeks) 29.9 31.5 29.0 29.9 29.3 29.9 27.9 28.9 26.9 26.1 26.1 25.1 28.1
  Valid to Decision (mean weeks) 32.5 34.9 32.7 33.3 32.0 32.5 30.2 30.5 28.5 28.7 27.9 26.5 30.9
  St. dev. of decision (weeks) 17.4 19.8 17.4 18.7 16.7 16.5 15.6 14.6 13.5 14.3 14.0 12.5 16.2
Enforcement Cases Valid to Decision (median weeks) 53.1 53.1 49.9 50.0 48.3 57.7 56.3 48.6 50.7 62.1 53.4 52.1 52.9
  Valid to Decision (mean weeks) 55.7 53.4 54.4 55.0 51.7 57.6 57.7 54.6 53.9 65.4 58.6 58.3 56.2
  St. dev. of decision (weeks) 21.1 22.3 26.5 24.7 23.0 22.6 25.3 30.1 27.3 29.7 26.6 30.3 26.2
Specialist Cases Valid to Decision (median weeks) 35.7 50.4 34.6 36.4 35.1 51.7 44.9 49.1 46.2 24.9 28.0 26.7 35.9
  Valid to Decision (mean weeks) 50.2 56.2 45.0 43.3 41.9 57.9 50.8 53.3 51.1 34.5 41.4 35.7 45.6
  St. dev. of decision (weeks) 37.8 36.9 37.5 32.7 26.9 42.3 33.4 32.0 31.4 26.4 32.7 28.3 33.9

Source: Horizon

Note: Specialist casework timeliness measures exclude Tree Preservation Order cases

Annex A gives information on median and mean time to decision, with standard deviation, for the three procedure types, split by planning, enforcement, and specialist casework categories.

Enforcement decisions made in the past 12 months had a median decision time of 53 weeks.

There are considerably fewer specialist cases which means results are more liable to be distorted by extreme values.

Figure 6 – Median Time to Decision by Casework Category: June 2023 to May 2024p.

Source: Horizon

Note: Specialist casework timeliness measures exclude Tree Preservation Order cases

Note that the Inspectorate publishes each month, information on the mean and median times from valid to decision, for selected appeal types. The information published also breaks down the time for each stage of the process. See Annex B for further details.

Planning Inquiry Decisions

For planning appeals decided by the inquiry process, The Planning Inspectorate has been implementing recommendations from the Rosewell review.

The median time for inquiries under Rosewell process over the 12 months to May 2024 is 30 weeks and the median time to decision for May 2024 was 30 weeks.

Table 8: Decisions, Mean and Median Time to Decision, Planning Inquiry Cases under Rosewell Process; June 2023 to May 2024.

Note 1: where there are fewer than 20 decisions, the measures mean, median and standard deviation are less meaningful.

Measure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Decisions 17 15 20 32 16 24 21 15 16 15 4 26 221
Median (weeks) 30.0 24.9 26.1 61.9 37.1 26.2 29.1 35.0 31.9 25.3 25.1 30.3 30.0
Mean (weeks) 34.3 30.0 33.9 47.1 35.2 31.6 44.2 36.0 31.2 27.2 25.7 35.6 35.9
St. Dev. (weeks) 25.8 12.2 17.0 16.2 9.0 11.7 23.0 9.3 7.9 7.0 1.9 15.0 16.6

Most inquiry decisions now being issued are under the revised ‘Rosewell’ process but some inquiries, for example those that are linked together with associated enforcement cases, do not follow the Rosewell process.

Table 9: Decisions, Planning Inquiry Cases under non-Rosewell Process; June 2023 to May 2024.

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Decisions 0 2 0 1 0 2 3 0 4 2 2 2 18

Source: Horizon

Figure 7 below shows the mean and median time to decision for planning inquiry cases under the Rosewell process.

Figure 7: Mean and Median Time to Decision, Rosewell Inquiry Process; June 2023 to May 2024.

Source: Horizon

5. Open Cases

At the end of May 2024, the Planning Inspectorate had 13,137 cases open. More information on the number of open cases, and how it has changed over the past 12 months, is in Table 2 and Figure 2 above.

The open cases comprised of 11,721 cases being handled through written representations; 907 through hearings; and 467 through inquiries, as well as 42 not currently allocated a procedure type. This is not the number of ‘live’ hearings and inquiries since it includes cases where the event (hearing or inquiry) has yet to start, as well as those where the event has finished but the decision has yet to be issued.

Data separating open cases into those that have and have not yet had an event is not available for the end of May. We are working to fix this problem and hope to restore that additional information to Table 10 in the next publication.

Table 10: Open cases by procedure and stage, as of end of May 2024

Stage WR HRG INQ Total
Case received but yet to be deemed valid 348 29 4 381
Case deemed valid but yet to “start” [Note 1] 2548 171 137 2856
Case started but decision not yet issued 8825 707 326 9858
Total 11721 907 467 13095

Source: Horizon

Note 1 - there are 42 cases that have no procedure type recorded (see Background Quality Report for more detail) These are included in the total but excluded from the breakdown by procedure.

Note 2 – there is a known anomaly that means that the number of open cases does not exactly follow the volumes of cases closed or received (for example the number of open cases can increase between months even though the number closed exceeded the number received). The main reasons for this have been identified and are detailed in the Background Quality Report.

6. Inspectors

Table 11 below shows the number of inspectors in the Planning Inspectorate in each month from May 2023 to April 2024 . This includes headcount (i.e. the number of different individuals) and full-time equivalents (FTE) where those working part time are counted in proportion with their contracted hours. There were 443 Planning Inspectors employed by the Inspectorate in May 2024 – with a full-time equivalent of 399.

Table 11: Planning Inspectors – Headcount and FTE; June 2023 to May 2024 (at end of month).

Month Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24
Headcount 428 439 437 432 430 428 426 424 426 434 443 443
FTE 384 394 393 388 386 385 384 382 383 391 400 399

Source: SAP HR and Employee Central

As above, Planning Inspectors work on a broader range of work than the appeals featured in this Release. Please note that data on Planning Inspectors is only applicable to salaried employees (it does not include fixed term contract Inspectors or Planning Appeal Decision Suppliers, previously referred to as non-salaried Inspectors).

7. Annex A – Mean and median time to decision, with standard deviation, for planning, enforcement, and specialist casework

Planning

Note 1: where there are fewer than 20 decisions, the measures mean, median and standard deviation are less meaningful. This applies to June, July and October 2023 and January, March and April 2024 for inquiries decisions.

Note 2: This table includes revisions to previously published data. Please see Annex C for further information

Procedure Measure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Written Representations Decisions 1187 1190 1186 1263 1344 1267 1141 1190 1351 1062 1165 1236 14582
  Median Average Weeks 29.9 31.8 29.1 29.7 29.3 30.0 27.9 28.9 26.9 26.4 26.1 25.1 28.3
  Mean Average Weeks 32.0 34.2 32.2 32.7 31.7 32.5 29.6 30.2 28.1 28.5 27.5 26.0 30.4
  Standard Deviation 16.4 18.1 15.7 17.7 15.8 16.4 14.4 13.8 12.8 13.6 12.3 11.3 15.2
Hearings Decisions 52 49 50 42 42 44 46 41 36 52 35 61 550
  Median Average Weeks 31.5 25.4 26.3 25.1 25.0 25.4 24.0 28.1 29.7 23.4 26.9 24.0 25.5
  Mean Average Weeks 42.9 50.7 43.4 38.0 39.5 31.4 38.2 38.9 35.5 31.2 37.2 30.1 38.0
  Standard Deviation 29.5 40.5 39.3 31.7 35.0 15.8 28.6 29.1 17.7 21.5 36.2 17.7 30.1
Inquiries Decisions 17 17 20 33 16 26 24 15 20 17 6 28 239
  Median Average Weeks 30.0 27.7 26.1 61.9 37.1 26.2 31.1 35.0 33.6 26.0 27.4 30.9 30.6
  Mean Average Weeks 34.3 36.1 33.9 50.2 35.2 34.4 45.4 36.0 38.5 34.9 46.5 41.9 39.5
  Standard Deviation 25.8 20.4 17.0 23.7 9.0 19.9 24.0 9.3 31.4 22.0 37.5 27.6 23.8
All Planning Cases Decisions 1256 1256 1256 1338 1402 1337 1211 1246 1407 1131 1206 1325 15371
  Median Average Weeks 29.9 31.5 29.0 29.9 29.3 29.9 27.9 28.9 26.9 26.1 26.1 25.1 28.1
  Mean Average Weeks 32.5 34.9 32.7 33.3 32.0 32.5 30.2 30.5 28.5 28.7 27.9 26.5 30.9
  Standard Deviation 17.4 19.8 17.4 18.7 16.7 16.5 15.6 14.6 13.5 14.3 14.0 12.5 16.2

Enforcement

Note: where there are fewer than 20 decisions, the measures mean, median and standard deviation are less meaningful. This applies to all months for hearing other than November 2023 and January 2024 and all months for inquiry decisions other than October 2023 and February, March, April and May 2024.

Procedure Measure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Written Representations Decisions 153 185 180 203 156 189 124 166 175 135 124 149 1939
  Median Average Weeks 52.9 51.9 48.2 47.6 49.4 55.3 54.5 46.1 49.3 58.6 50.5 52.9 51.6
  Mean Average Weeks 53.7 51.9 51.9 51.0 52.8 55.2 54.5 51.4 51.5 61.1 53.5 57.7 53.6
  Standard Deviation 17.3 21.3 22.3 19.7 22.9 19.9 19.0 24.6 23.2 25.4 25.2 28.3 22.6
Hearings Decisions 6 11 9 12 11 22 15 23 11 19 16 16 171
  Median Average Weeks 50.5 34.0 58.3 71.5 61.0 63.8 62.3 69.7 60.9 71.7 87.6 43.8 62.3
  Mean Average Weeks 56.6 50.4 74.8 81.1 56.6 66.7 66.3 71.7 69.4 74.8 87.0 46.8 67.8
  Standard Deviation 25.1 24.8 40.6 36.0 27.0 29.5 26.2 48.1 28.4 37.8 19.0 28.8 35.0
Inquiries Decisions 7 12 3 9 20 17 12 17 22 23 40 22 204
  Median Average Weeks 101.3 80.1 146.1 94.6 46.3 72.7 69.4 81.0 50.6 90.6 47.1 77.9 72.9
  Mean Average Weeks 98.2 78.6 146.1 110.2 40.3 73.3 80.5 63.0 65.2 83.0 63.1 70.5 71.4
  Standard Deviation 39.2 19.8 0 20.2 17.0 29.9 52.6 37.1 45.4 36.4 25.5 38.6 38.1
All Enforcement Cases Decisions 166 208 192 224 187 228 151 206 208 177 180 187 2314
  Median Average Weeks 53.1 53.1 49.9 50.0 48.3 57.7 56.3 48.6 50.7 62.1 53.4 52.1 52.9
  Mean Average Weeks 55.7 53.4 54.4 55.0 51.7 57.6 57.7 54.6 53.9 65.4 58.6 58.3 56.2
  Standard Deviation 21.1 22.3 26.5 24.7 23.0 22.6 25.3 30.1 27.3 29.7 26.6 30.3 26.2

Specialist

Note: where there are fewer than 20 decisions, the measures mean, median and standard deviation are less meaningful. This applies to all months’ hearings decisions; and all months inquiries decisions.

Procedure Measure Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Total
Written Representations Decisions 57 42 24 49 57 36 48 50 33 133 58 57 644
  Median Average Weeks 31.9 48.6 23.6 28.1 34.0 43.6 40.7 42.4 42.3 23.4 25.7 26.7 31.3
  Mean Average Weeks 47.7 50.9 31.6 40.4 40.6 49.0 45.7 48.9 45.5 31.4 39.3 32.6 41.0
  Standard Deviation 38.3 33.3 20.7 33.5 27.6 35.0 29.2 29.4 28.6 23.9 33.5 24.9 30.9
Hearings Decisions 1 5 4 4 1 0 3 3 2 8 0 1 32
  Median Average Weeks - 70.9 63.8 37.2 - - 65.6 57.1 79.9 77.9 - 100.7 63.9
  Mean Average Weeks - 70.0 61.9 37.2 - - 65.6 57.1 79.9 82.1 - 100.7 68.6
  Standard Deviation - 12.2 16.4 1.1 - - 0 7.8 21.4 28.2 - 0 22.4
Inquiries Decisions 5 5 5 4 4 6 7 3 2 3 6 1 51
  Median Average Weeks 68.3 42.7 65.9 59.9 47.1 93.6 78.4 113.6 101.9 50.1 52.6 104.6 66.1
  Mean Average Weeks 71.7 71.9 90.6 68.9 50.2 103.9 72.3 111.8 101.9 52.1 57.1 104.6 76.9
  Standard Deviation 23.9 58.4 59.4 21.9 20.7 46.6 43.1 16.6 1.2 14.2 19.4 0 41.9
All Specialist Cases Decisions 63 52 33 57 62 42 58 56 37 144 64 59 727
  Median Average Weeks 35.7 50.4 34.6 36.4 35.1 51.7 44.9 49.1 46.2 24.9 28.0 26.7 35.9
  Mean Average Weeks 50.2 56.2 45.0 43.3 41.9 57.9 50.8 53.3 51.1 34.5 41.4 35.7 45.6
  Standard Deviation 37.8 36.9 37.5 32.7 26.9 42.3 33.4 32.0 31.4 26.4 32.7 28.3 33.9

Tree Preservation order decisions have been removed from the average time calculations in this table due to problems with recorded validation dates, which mean that we are currently unable to accurately calculate their decision times.

8. Annex B – Detailed Information on timeliness (May 2024)

The information below is published today on the number and length of decisions made in May 2024 :

Note 1: when there are fewer than 20 decisions the measures mean, median and standard deviation are less meaningful

Casework Type Procedure Type Median (weeks) Mean (weeks) Decisions
s78 planning appeals Written Representations 27.6 29.8 749
s78 planning appeals Hearings 23.6 30.1 59
s78 planning appeals Inquiries 30.9 41.9 28
Householder appeals Written Representations 15.9 18.8 395
Enforcement appeals Written Representations 52.9 57.7 149
Enforcement appeals Hearings 43.8 46.8 16
Enforcement appeals Inquiries 77.9 70.5 22

The smaller the number of decisions, the less helpful the mean and median are as measures for summarising performance. Particular care should be taken when there are fewer than twenty decisions.

The information published below shows the time taken for different stages of the appeals process:

s78 planning appeals s78 planning appeals s78 planning appeals Householder appeals
  Written Representations Hearings Inquiries Written Representations
Weeks between valid date & start date        
Median (average) 8.2 3.9 2.0 4.1
Mean (average) 7.7 7.5 3.1 4.8
Cases that started in April 2024 940 54 16 411
Weeks between start date & event date        
Median (average) 12.3 13.7 16.0 8.7
Mean (average) 14.2 19.1 17.0 9.9
Cases where an event occurred during April 2024 685 43 13 338
Weeks between event date & decision date        
Median (average) 4.0 3.4 12.2 3.0
Mean (average) 5.4 5.4 15.0 4.2
Cases that have been decided in April 2024 745 59 28 394

Note: Only cases with both dates recorded appear in this table, meaning that numbers for cases decided and events recorded may be lower than those presented elsewhere.

Explanation of date terminology

Valid date When a case is deemed to have been validly received.  Note – this is not always the date the case was validated. If a case is validated after the date it was validly received, it is the date it was validly received that is the valid date.
Start date When a timetable, on how the appeal will progress, is issued to both the appellant and local authority. This timetable tells the appellant when to submit the information the Inspectors need to determine the appeal. It also tells the local authority when to notify interested parties about the appeal.
Event date When the site visit, hearing, or inquiry occurred.
Decision date When the decision was issued by The Planning Inspectorate.

Find out more about the process here - https://www.gov.uk/appeal-planning-decision/after-you-appeal

9. Annex C – Revisions to the data tables

This Annex lists all revisions made to the data since the last statistical release.

Note: Classed as a revision are any values which have changed by more than five (when measuring number of decisions/ cases) or more than 0.5 weeks (for mean, median or standard deviation of weeks).

Timeliness measures for all 12 months have been reproduced without Tree Preservation Order cases in this publication. This is due to problems with recorded validation dates, which mean that we are currently unable to accurately calculate their decision times.

Table Revisions
Table 1 Events held: April 2024
Table 2 Open cases: August, September and October 2023, March and April 2024
Table 6 Inquiries Valid to decision (Median weeks): March 2024
Table 6 Inquiries Valid to decision (Mean weeks): March 2024
Annex A Planning Hearings Median weeks: January 2024
Annex A Planning Hearings Mean weeks: January 2024
Annex A Enforcement Inquiries Mean weeks: March 2024
Annex A Enforcement Inquiries Standard Deviation: March 2024
Annex A Specialist Written Reps Median weeks: March 2024

10. Background notes

Data sources

Horizon / Picaso – The main casework management systems used for processing appeals casework (note that Picaso is no longer a live system).

SAP HR – The Human Resources system database used to store all information regarding members of staff.

Compliance with the Code of Practice for Statistics

These statistics have been published in accordance with the Code of Practice for Statistics, which cover trustworthiness, quality, and value. They have been pre-announced, and publication is overseen by the Head of Profession.

10.1 Technical Notes

A Background Quality Report is published alongside this Statistical Release. It provides more detail on the quality of statistics in this publication.

Data quality

Data on cases is taken from a live casework system, and details of cases can change for a number of reasons even after a decision has been made. We are seeking to get a better understanding of the nature and volume of these changes and will provide further information as it is available.

We carry out regular checks on the quality of our data and may undertake ad hoc data cleansing exercises.  Therefore, all the data for the last 12 rolling months is published in provisional form.

We have indicated in this publication any data where a number of cases has changed by more than five cases in a month; or where a measure (mean, median or standard deviation) has changed by more than 0.5 weeks.

Measuring weeks

Data are measured in days and then converted to weeks.

Note that not all decimal values are possible where converting days to weeks. 1 day is 1/7 of a week, or 0.14 weeks (to two decimal places). 2 days = 0.29; 3 days = 0.43; 4 days = 0.57; 5 days = 0.71; 6 days = 0.86.

When these are used to calculate averages, or displayed to one decimal place, the result will not equate to a full day which can be misleading: it may appear that we are measuring part days (e.g. 19.8 weeks) but we only measure in whole days.

Glossary

Term Explanation
Appeals The right to appeal a planning decision made by a local authority is a key feature of the planning system, as is appealing when an authority is taking too long.
Appeals decided Number of appeals by the date the appeal was decided by The Planning Inspectorate.
Appeals received Number of appeals by the date the appeal was received by The Planning Inspectorate.
Applications Planning Inspectorate manage the application process for proposed Nationally Significant Infrastructure Projects (NSIPs) within England and Wales in line with the 2008 Planning Act.
Closed The total number of appeals decided, withdrawn, or turned away.
Decision The outcome of the case e.g. appeal allowed or rejected. The date of the decision is taken as the date a decision letter is sent to the appellant.
Event A site visit, hearing, or inquiry (may be virtual)
Event Type The different options of how an Inspector visits a site for a written representations appeal.
Examinations The process of examining local plans is dealt with by the Planning Inspectorate. Every Local Planning Authority is required to have a local plan.  This includes a vision for the future and plan to address housing needs in the area.
Examinations When a Local Planning Authority has finished preparing and consulting on a local plan it must be submitted to the Secretary of State who appoints an Inspector to carry out an independent examination.
FTE Full Time Equivalent – a count of employees where those working part time are counted in proportion with their contracted hours.
Headcount Total number of staff employed regardless of how many hours they work (i.e. the number of different individuals).
Hearings A hearing involves the submission of written evidence by the main parties and a hearing once all the written submissions have been received.
Hearings This takes the form of a round-the-table discussion (in person or virtually) that will be led by the planning inspector. It allows for all parties to respond to any questions that the inspector might have, and to let everyone make their case known.
Hearings Source: Planning Portal
Inquiries An inquiry is usually used for complex cases where legal issues may need to be considered. The main parties will usually have legal representatives to present their case and to cross-examine any witnesses. Prior to the inquiry date, the Planning Inspectorate will expect to have received various documents from all parties that will be taking part in the appeal. These may include statements of case and proofs of evidence from expert witnesses. Third parties may also take part. The inquiry will be led by the inspector and will follow a formal procedure.
Inquiries At some point during or on conclusion of the inquiry the inspector and the main parties will undertake a site visit.
Inquiries Source: Planning Portal
Live appeals Number of live appeals in that have an appeal valid date but no end date (either decision date or a closed date, e.g. for appeals that have been withdrawn).
Mean The total time taken divided by the number of cases. Also referred to as the ‘average’. A measure of how long each case would take, if the total time taken was spread evenly across all cases.
Median This is the time taken by the ‘middle’ case if all cases were sorted from quickest to longest
Open Cases Number of cases that have been received but on which a decision has not yet been made/ issued. Will differ from Live Appeals as it includes those received but not yet verified.
Procedure Type The method by which The Planning Inspectorate processes and decides appeals.
Standard deviation This is a measure of variability or spread. It is calculated by examining how much each value differs from the mean. A higher standard deviation means the individual decision times vary more widely around the mean.
Written Representations Most planning appeals are decided by the written representations’ procedure. With this procedure the Inspector considers written evidence from the appellant, the LPA and anyone else who has an interest in the appeal. The site is also likely to be visited.

11. Contact Us

The Planning Inspectorate welcome feedback on our statistical products. If you have any comments or questions about this publication or about our statistics in general, you can contact us as follows:

Media enquiries 0303 444 5004 email press.office@planninginspectorate.gov.uk

Public enquiries email statistics@planninginspectorate.gov.uk

Please note we are currently reviewing our statistics with a view to making them as clear and helpful as possible for users. We would be delighted if you could contact us via the address below with any views on this approach; particularly on what content would be most useful and why.

email statistics@planninginspectorate.gov.uk

If you require information which is not available within this or other available publications, you may wish to submit a Request for Information under the Freedom of Information Act 2000 to the Planning Inspectorate. For more information, see: https://www.gov.uk/make-a-freedom-of-information-request/the-freedom-of-information-act