Guidance

Section 62A Planning Application: S62A/2024/0045 Land at Wickham Hall Estate, Bishops Stortford, Uttlesford, CM23 1JG

Overview of case details, documents, key dates and how to make a representation.

Applies to England

Type of application:

Full Planning Application

Applicant name

Endurance Energy and Wickham Hall Ltd

Site address:

Land at Wickham Hall Estate, Bishops Stortford, Uttlesford CM23 1JG

Description of proposed development

Erection of a Solar Photovoltaic Farm with supporting infrastructure and battery storage, inverters and transformers, fencing, landscaping works and connecting cable.

Case Officer

Section 62A Applications Team

Procedure

TBC

Key dates

Date
Date application valid 20 June 2024
Date by when representations must be made 25 July 2024
Hearing date and venue TBC
Target decision 19 September 2024
Decision date TBC

Hearing Documents

Decision

Make a representation

The application can be inspected under the application plans and documents heading below.

You will be able to comment on this application until 25 July 2024

Please base your comments on planning matters.

Please avoid the use of inflammatory, discriminatory or abusive comments

All representations made in connection with the development proposal will be made publicly available on the website shortly after the end of the representation period.  The name of the individual author or organisation will be published however addresses, signatures and contact details will not be published.  We advise you not to include any other personal information about yourself or others. 

Our Customer Privacy Notice sets out how we handle personal data in accordance with the law.

Send your comments via email to section62a@planninginspectorate.gov.uk

or write to

Section 62A Applications Team,
The Planning Inspectorate,
3rd Floor, Temple Quay House,
2 The Square, Temple Quay,
Bristol,
BS1 6PN

Sending comments by email will enable us to deal with them more quickly and is preferred.

Please include the application reference number and site address.

This application will be determined by an Inspector appointed by the Secretary of State.  Shortly after the close of the representation period the Planning Inspectorate will consider whether a hearing is necessary.   In the event that a hearing is scheduled, and you would wish to speak at the hearing, you must make this request at the time you submit your written representations.

Where the application is to be considered at a hearing, notice of the date, time and venue for the hearing along with the name of the person holding the hearing, will be published on this website at least two weeks before the date of the hearing. 

Application Plans and Documents

Questionnaire and supporting documents

Comments

Consultees

Interested Parties

Planning Inspectorate Correspondence

Applicant Correspondence

Published 26 June 2024
Last updated 26 June 2024 + show all updates
  1. PS appendices 1.3 & 3 added under application plans and documents

  2. First published.