Small Modular Reactors: technology selection process
Progress of GBN's Small Modular Reactor (SMR) technology selection process.
In July 2023, GBN issued a Contract Notice setting out an intention to enter into a two Stage contract for design, development and construction contract with those successful bidders.
Procurement Progress To-Date
-
In July 2023, interested parties were required to respond to a selection questionnaire. This concluded in August 2023.
-
In October 2023, GBN down-selected six technologies, who would be eligible to bid into the next phase of the procurement.
-
In March 2024, these six vendors were invited to submit initial tenders. GBN received five bids by the July 2024 submission deadline.
-
In September 2024, GBN concluded the initial tender phase of the technology selection process. The down-selected companies are:
-
GE-Hitachi Nuclear Energy International LLC
-
Holtec Britain Ltd
-
Rolls Royce SMR Ltd
-
Westinghouse Electric Company UK Ltd
5.In October 2024, GBN issued an Invitation to Negotiate to the four companies.
6.In February 2025, GBN issued an Invitation to Submit Final Tenders. Once final tenders are received, GBN will evaluate these, with final decisions on which technologies to select to be taken in the spring.
Contact details
If you have any questions about SMRs or GBN, email enquiries@gbnuclear.gov.uk
Updates to this page
-
Yes, an update on the SRM selection process.
-
Update on the SMR technology selection process
-
GBN has updated the information regarding the initial tender phase of the technology selection process.
-
Added link to the Small Modular Reactor Technology Partner contract notice on GOV.UK Find a tender service.
-
First published.