Guidance

Combined Heat and Power Quality Assurance Programme

Certification for Good Quality CHP and CHPQA financial incentives.

What is CHPQA

The CHP Quality Assurance programme (CHPQA) is a government initiative providing a practical, determinate method for assessing all types and sizes of Combined Heat and Power (CHP) schemes throughout the UK. CHP, the simultaneous generation of heat and power in a single process, provides one of the most cost-effective approaches for making carbon savings and plays a crucial role in the UK Climate Change programme.

CHPQA aims to monitor, assess and improve the quality of UK Combined Heat and Power.

While participation in the CHPQA programme is voluntary, the government is committed to increasing the UK’s CHP capacity because of the considerable environmental, economic and social benefits it can bring together with its contribution to security of supply. Successful CHPQA certification grants eligibility to a range of benefits, including Renewable Obligation Certificates, Renewable Heat Incentive, Carbon Price Floor (heat) relief, Climate Change Levy exemption (in respect of electricity directly supplied), Enhanced Capital Allowances and preferential Business Rates.

CHPQA, by assessing CHP schemes on the basis of their energy efficiency and environmental performance, ensures that the associated fiscal benefits are in line with environmental performance.

The programme is carried out on behalf of the Department for Energy Security and Net Zero (DESNZ), in consultation with the Scottish Executive, the National Assembly for Wales, and the Northern Ireland Department of Enterprise, Trade and Investment and has been running since 2001.

The CHPQA Standard sets out definitions, criteria and methodologies for the operation of the programme. It should be read in conjunction with the supporting CHPQA Guidance Notes, which provide detailed information on how this Standard will be interpreted by government departments and agencies as well as guidance on compliance with this Standard.

Applying to CHPQA

The first step in the route to CHPQA certification is to register for the programme by completing Form F1.

Form F1 is a basic administration form used to record the address of a proposed or existing CHP scheme and the contact details of the RP with whom all resultant CHPQA correspondence will be made, and is the first form that needs to be completed.

This form must be signed by the RP prior to submitting. If the RP is responsible for more than one CHP scheme, only one F1 form needs to be submitted but a list of the relevant scheme addresses must be attached.

Following the receipt of Form F1, the CHPQA administrator will send the RP a unique reference number for the scheme(s) and a user name and password.

These are required to access the online electronic submission system. Note that CHPQA applications may also be submitted on paper if preferred, though the online system is much simpler.

Following receipt of reference number and login details for the electronic submission system, the next step in the submission procedure is, in part, dependant on the complexity of the scheme, is it a ‘simple’ or ‘complex’ scheme.

CHPQA online submission

All self assessment forms can be completed online. Use CHPQA online submission system for CHPQA certification.

CHPQA guidance notes

CHPQA guidance notes are available for completing CHPQA forms.

‘Simple’ scheme submission forms

A scheme is defined as ‘simple’ if it meets the following criteria:

  • generating capacity < 2 MWe
  • single reciprocating engine
  • single conventional fuel used
  • no heat only boiler present

Then the shortened versions of the CHPQA forms can be used which simplifies the submission procedure. These are denoted by the letter ‘s’ following each form name e.g. F2(s), F3(s) and F4(s). There are 2 categories of simple schemes: existing and new.

Simple schemes: existing

If your scheme is already commissioned and running and you have sufficient operational data for at least one month, then you need to complete Form F2(s) and F4(s).

  • Form F2(s) – this is used to provide details of the CHP scheme, such as installed equipment capacity, type, etc, and metering arrangements. Note: Form F2(s) only needs resubmitting if changes are made to the scheme.

  • Form F4(s) – If your scheme has at least one month of operational data, this form is used to provide details of the scheme’s actual performance. You only need to submit the annual energy figures for:

    • Electricity generated
    • Fuel consumed
    • Heat utilised

Where the scheme is <500 kWe with no appropriate gas metering, the fuel input may be estimated based on power efficiency using the CHPQA ‘Unit List’ which can be found on the CHPQA website.

Note: Form F4(s) is resubmitted each year with scheme performance details for the previous calendar year enabling a new CHPQA certificate to be issued. If there are any significant changes to the scheme (e.g. boundaries, metering) a new Form F2(s), must also be resubmitted.

Simple schemes: new

Form F3(s) is for self-assessment of schemes which are not yet operational enabling you to provide technical details and anticipated performance, based on design information prior to commissioning. It is not a requirement to complete a F2(s) at this stage.

It also allows you to request an energy efficiency certificate for the scheme that is used in claiming Enhanced Capital Allowances (ECAs). If a Certificate of Energy Efficiency is required you need to tick the box at the bottom of the declaration of the F3(s) form, provide a list of identified potential electricity customers and complete part 5.

Note: Form F3(s) is resubmitted each year enabling a new CHPQA certificate to be issued, where there is no change from the previous calendar year, this may be reflected by entering “as in F3(s) Self-Assessment for 20xx”.

The CHPQA certificate provided will be valid until the 31 December of the year of issue.

‘Complex’ scheme submission forms

The sequence of forms is the same as for the ‘simple’ scheme submission, however more detail is required and thus the forms are longer. The descriptor ‘complex’ therefore covers all other schemes that are not ‘simple’:

A scheme is complex if it meets any of the following:

  • generating capacity superior or equal to 2 MWe
  • prime mover not a single reciprocating engine
  • non-conventional fuel used
  • fired boiler(s) included within scheme boundary

Complex schemes: existing

If your scheme is commissioned and running and you have sufficient operational data, then Form F2 and F4 must be completed.

  • Form F2 – this form is used to provide a description of the scheme. This requires a list of all installed equipment (prime movers, boilers, their capacity, type, age etc) and metering equipment that will be used to monitor the performance of the CHP scheme. You will also need to provide scheme schematics showing all the listed equipment and meters.

  • Form F4 – If your scheme has at least one month of operational data, this form is used to provide details of actual performance. You need to submit the following monthly energy figures:

    • Electricity generated
    • Fuel consumed
    • Heat utilised

You will also need to submit more supporting documentation than for simple schemes. This may include additional calculations necessary for determining the overall efficiency (the “Quality Index”) of the scheme.
Note: Form F4 is resubmitted each year with scheme performance details for the previous calendar year enabling a new CHPQA certificate to be issued.

Complex schemes: new

If your scheme is still at the design stages, under construction or you don’t yet have sufficient operational data, then you have to complete Form F3.

The procedures are otherwise the same as for new simple schemes outlined above. You can access all CHPQA paper forms.

CHPQA certificates

You may use your CHPQA Certificate to support a claim for the benefits offered to Good Quality CHP.

To use CHPQA to claim Climate Change Levy (CCL) exemption on fuel inputs to and power outputs from, your CHP Scheme you must also have a Secretary of State (combined heat and power) exemption Certificate for your CHP Scheme. Confirmation that a SoS (CHP) exemption certificate is required is done by completing the appropriate section of the CHPQA F3 or F4 submission form.

To use CHPQA to claim Enhanced Capital Allowances (ECAs), you must have a Secretary of State Certificate of Energy Efficiency. This is requested for by completing the appropriate section of the CHPQA F3 submission form.

CHPQA timescales

CHPQA is an annual certification process. Shortly after the end of each calendar year, it is necessary for the RP to:

  • compile the CHP scheme energy data that was monitored over the previous year
  • assess the scheme’s performance
  • submit the resultant figures on the appropriate forms for validation to CHPQA

RPs wishing to renew their CHPQA Certificate are encouraged to submit the completed forms by the end of March, allowing the CHPQA Administrator time to validate their forms and issue a new certificate in good time for the SOS Certificate to be maintained by BEIS at the end of June deadline.

While the Administrator will accept forms beyond March, there is a risk that this delay will result in this deadline being missed. This means entitlement to CCL exemption will be removed from the beginning of the calendar year up until the time a new SOS (CHP) exemption Certificate is issued.

Certification timetable

  • CHPQA Certificates cover a calendar year and expire at the end of December
  • SOS (CHP Exemption) certificates are open ended, provided that a valid CHPQA certificate is obtained by no later than end of June every year.

Contact CHPQA

CHPQA programme

The CHPQA Administrator
The Gemini Building
Fermi Avenue
Didcot
OX11 0QR

Email chpqainfo@chpqa.com

CHPQA Helpline Number 01235 75 3004

The Helpline Number is open Mon to Fri 9am - 4pm

Case studies

A series of CHP case studies are available.

CHPQA past events

The CHPQA workshop and seminar 2023

In December 2023, the Combined Heat and Power Quality Assurance Programme held 4 online workshops and 1 in-person workshop for registered CHPQA programme users. The workshops were split across 2 modules, with 3 workshops held on Module 1 and 3 workshops held on Module 2.

Module 1 provided an overview of the principles, benefits and procedures of CHPQA, the submission process was explained, using online submission system examples, covering the data required, and the CHPQA metering requirements were explained.

Module 2 covered the fiscal benefits for GQCHP, how these interact with CHPQA and recent developments for both conventionally and renewably fuelled CHP schemes.

The presentations delivered during the CHPQA workshop and seminar 2023 are available to download.

UK National Comprehensive Assessment stakeholder event

Following the publication of the UK’s National Comprehensive Assessment for high-efficiency CHP and efficient district heating and cooling, DECC held a stakeholder event on 15 April 2016 at which the final results were presented by Ricardo Energy & Environment who undertook the study. The presentations delivered during the event are available to download.

National comprehensive assessment presentation (PDF, 2.84 MB, 65 pages)

Read the full NCA report.

Updates to this page

Published 1 August 2014
Last updated 5 September 2024 + show all updates
  1. Link added to the latest (2023) CHPQA workshop.

  2. A link has been provided to the presentations delivered at the latest CHPQA workshops held in November 2019.

  3. The 2019 CHPQA workshop events have been announced and the associated event registration form attached.

  4. CHPQA Workshop and Seminar 2018 presentation have been published.

  5. CHPQA workshop and seminar 2018 announced

  6. CHPQA Event presentations are published.

  7. November 2017 events announced.

  8. CHP Case Studies have been uploaded

  9. CHPQA workshop and presentations have been uploaded

  10. CHPQA events in November

  11. Published CHPQA workshop and seminar presentations

  12. Additional date for the CHPQA Event

  13. CHPQA Events date has been changed.

  14. CHPQA Event announced

  15. First published.