Carbon Capture Readiness – CO2 storage site: Indefatigable Gas Field
Areas identified for potential usage in CCR reports.
Documents
Details
Field name: Indefatigable Gas Field
Estimated total CO2 storage capacity (tonnes): 357,000,000
Potential capacity identified in CCR reports (tonnes):
- 131,000,000
- 223,000,000
Potential user:
- Sutton Bridge B CCGT
- Eggborough CCGT
‘Remaining’ CO2 storage capacity (tonnes): 3,000,000
An applicant’s choice of storage area at the CCR stage is not binding. It therefore follows that an applicant’s choice of storage area at the CCR stage does not confer priority on that applicant for use of that storage area when CCS is deployed on their power station. Operators will be required to obtain a permit from the department and a lease from the Crown Estate in order to store CO2 offshore when CCS is operational.